Jeffco Builds Finishes A Strong Year and Looks Ahead to 2023

Jeffco Builds Begins 2023 Roughly 84% Complete and Ahead of Schedule
Posted on 01/19/2023
This is the image for the news article titled Jeffco Builds Begins 2023 Roughly 84% Complete and Ahead of Schedule

Jeffco's Capital Improvement Program is beginning 2023 roughly 84% complete and largely ahead of schedule. We just wrapped up a banner year in which many of our large projects were completed.

Our schools' improvements were made possible by Jefferson County voters who approved bond money in 2018. Since then, Jeffco Builds has been hard at work to improve our schools and strengthen our community.

Today, the majority of our projects have been completed ahead of schedule. In addition, thanks to good financial management and profitable investments, the district will also make use of $118 million more than expected at no extra cost to taxpayers. Jeffco Schools will complete every promised project and then some!

Jeffco Builds Capital Improvement Project Status

Some of the additional projects include an addition at D'Evelyn Jr./Sr. High School; buildout of JeffcoNET, our district's own fiber network; funding of Jeffco charter schools; and improvements to Trailblazer Stadium, one of four large stadiums that hosts athletic events for the entire district.Initial Bond Added Value

What We Accomplished in 2022

Replaced School Buildings

Additions to existing schools

Elementary schools who received efficiency and future-ready improvements

Bergen Valley Elementary School
Blue Heron Elementary School 
Colorow Elementary School
Elk Creek Elementary School
Emory Elementary School
Green Mountain Elementary School
Mitchell Elementary School
Mortenson Elementary School
Peck Elementary School
Red Rocks Elementary School 
Secrest Elementary School 
Shaffer Elementary School
Shelton Elementary School 
Slater Elementary School
Stevens Elementary School
Stony Creek Elementary School
Thomson Elementary School 
Ute Meadows Elementary School
Warder Elementary School
West Jeff Elementary School
Westgate Elementary School
Wilmore Davis Elementary School

Middle and high schools who received efficiency and future-ready improvements

Creighton Middle School 
Mandalay Middle School
North Arvada Middle School
Arvada West High School
Bear Creek High School
Golden High School
Lakewood High School
Long View High School 
Wheat Ridge High School
Warren Tech North 

Outdoor lab schools who received efficiency and future-ready improvements

Mt Evans Outdoor Lab School
Windy Peak Outdoor Lab School

On the Horizon in 2023

Several schools around the district will see major additions or renovations over the next year:

  • Jeffco Open School auditorium (opening spring 2023)
  • Standley Lake auxiliary gym and energy-efficiency upgrades (opening spring 2023)
  • Ralston Valley High School classroom and library addition (expected opening fall 2023)
  • Efficiency and future-ready improvements at 30 schools

Elementary schools receiving efficiency and future-ready improvements

Campbell Elementary School
Edgewater Elementary School 
Glennon Heights Elementary School
Governor's Ranch Elementary School
Kendallvue Elementary School
Little Elementary School 
Molholm Elementary School 
Mount Carbon Elementary School
Parr Elementary School 
Peiffer Elementary School 
Pennington Elementary School
Rose Stein Elementary School
Sierra Elementary School
South Lakewood Elementary School
Swanson Elementary School
Van Arsdale Elementary School 
Weber Elementary School

K-8, middle and high schools receiving efficiency and future-ready improvements

Bear Creek K-8
Coal Creek Canyon K-8
Connections Learning Center
Deer Creek Middle School
Drake Middle School
Dunstan Middle School 
Falcon Bluffs Middle School
Ken Caryl Middle School
Moore Middle School
Oberon Middle School
Sobesky Academy
Summit Ridge Middle School
Warren Tech Central

Ongoing Projects

The bond money is also being used to fund ongoing districtwide enhancements to improve the health, safety and efficiency of our schools. We're continuing our progress on several projects:

  • Providing high speed internet access to all Jeffco Schools through a district owned fiber network, JeffcoNET, to allow the district to be independent from outside providers
  • Upgrading to LED lighting in our schools to improve their energy efficiency
  • Improving safety and security in our schools

We'll keep you updated on our progress this year on the Jeffco Builds website.